More commuters traversing Quezon City up north and Parañaque City down south will enjoy shorter travel time, thanks to the first phase of the Light Rail Transit-Line 1 (LRT-1) Cavite extension, according to the Philippine office of the Japan International Cooperation Agency (JICA). In a...
President Marcos said that Filipino commuters will now see a great reduction in travel time in Metro Manila as he led the inauguration of the Light Rail Transit Line 1 (LRT-1) Cavite Extension Project (L1CE) Phase 1, marking a significant milestone in modernizing the transport system in the...
The Department of Transportation (DOTr) announced on Thursday, Nov. 7, that the Phase 1 of the Light Rail Transit-1 (LRT-1) Cavite Extension will be operational starting this month. The start of test runs for Phase 1 of the LRT-1 Cavite Extension project (Photo from the Light Rail Manila...
LRT-1 (File photo: Light Rail Manila Corporation) The Light Rail Transit 1 (LRT-1) will suspend its services for three weekends to facilitate the preparations for the LRT-1 Cavite Extension Phase 1, which is set to launch by the end of 2024. The LRT-1 announced on Friday, Aug. 9, that there will be...
Finance Secretary Ralph G. Recto said that the railway connecting Cavite and Metro Manila will create more jobs and business opportunities in the south. Recto, the government's chief economic manager, said that the first phase of the Light Rail Transit (LRT) Line 1 (South) Cavite extension project...
Passengers are now expected to cut their traveling time between Quezon City and Parañaque from an hour and a half to just 25 minutes with the addition of five new stations to the LRT Line 1 Cavite Extension. This is just the first of the remaining stations in the Cavite leg that have yet to be...
LRT-1 Dr. Santos Station in Parañaque City (Photo courtesy of Parañaque Cong. Edwin Olivarez / Facebook) The partial operation of the Light Rail Transit (LRT)-1 Cavite extension is expected to begin in the fourth quarter of this year as the rail project’s first phase is now 98.2 percent...
The fare going from Quezon City to Parañaque City through the Light Rail Transit (LRT) Line 1 Cavite Extension will cost less than jeepneys and bus fares, an official from the Department of Transportation (DOTr) said. During a site visit on Friday, June 7, DOTr Assistant Secretary for Railways...
The Parañaque Traffic Parking and Management Office (TPMO) said a portion of Ninoy Aquino Avenue will be temporarily closed on Aug. 19 to 22 due to construction of Ninoy Aquino Station of LRT I Cavite Extension Project. According to the Facebook post of TPMO, northbound and southbound lanes near...
64196 The first phase of the P65-billion LRT-1 Cavite Extension is 67.5 percent complete as of end December 2021 and is expected to start partial operations in the first quarter of 2024 yet, the Light Rail Manila Corporation (LRMC) announced. In a statement Monday, Feb. 7, LRMC said that Phase 1 of...
The P64.9-billion Light Rail Transit (LRT)-1 Cavite Extension, which was delayed for two decades, is 61.60 percent complete as of December 2021, according to the Department of Transportation (DOTr). media The National Economic Development Authority (NEDA)- Investment Coordination Committee ( ICC)...
The Light Rail Transit (LRT-1) Cavite Extension project has achieved a completion rate of over 50 percent under the Duterte administration. (Photo from Art Tugade's Facebook) Department of Transportation (DOTr) Secretary Arthur Tugade made this revelation over the weekend in his Facebook account,...