Luzon and Visayas grids are having a race against time when it comes to capacity additions – that is if the country has to seriously avoid the dire consequences of threatening power crisis into these two major power grids. The Philippine Independent Power Producers Association Inc. (PIPPA)...
Wheeling of generated capacities from power plants sited in the southern part of Luzon could be impeded if delays in the 500-kilovolt (kV) Tuy-Dasmarinas transmission line project of the National Grid Corporation of the Philippines (NGCP) could not be avoided due to pending legal hurdles, primarily...
Power supply in the Luzon system is still at its ‘fragile state’, prompting system operator National Grid Corporation of the Philippines (NGCP) to declare fresh wave of ‘yellow alert’ condition in the grid on Wednesday (April 17) as 18 electric generating units are still on forced outages....
The sudden forced outages at the units 1 and 2 generating units of the Kalayan hydropower plant in Laguna past 4:00pm on Tuesday served as the final trigger to the rotational brownouts that had been scheduled in some provinces in the Luzon grid. By 4:15pm, system operator National Grid Corporation...
As it is becoming apparent that the government may have been failing on its projection of ‘no red alert’ and sufficient power supply within the stretch of the summer months, the Department of Energy (DOE) is appealing to the industrial and commercial end-users in particular to pare their...
Senator Lito Lapid has reiterated that using renewable energy (RE) sources can help address the brownouts being experienced in Negros Occidental, Panay Island, and other areas in the country. Lapid said the country must improve usage of RE sources such as solar, wind, and hydropower. Using...
The 14-megawat second phase of the Nabas wind farm project of Yuchengco-led PetroWind Energy Inc. (PWEI) has started shoring up power supply for the energy-strained Panay island after securing warranted clearances from relevant authorities and entities in the market. Prior to its injection of...
With pronouncements from the Philippine Atmospheric, Geophysical and Astronomical Services Administration (PAGASA) that the El Niño phenomenon may not be as worse as earlier predicted, the Department of Energy (DOE) is expecting that strain in the country’s power supply would also be moderated...
As the country’s power supply is still at its wobbly state, the Department of Energy (DOE) guaranteed that it will conscientiously monitor the overall operations of the power grid so consumers can be alerted on any service interruptions and for relevant industry players to correspondingly sort...
Around P1 billion of funding has been approved for providing power supply to public schools that do not have electricity. The Department of Budget and Management (DBM) has released a total of P1.295 billion of special allotment release order (SARO) to the Department of Education (DepEd) to cover...
TORONTO – Long term power supply agreements (PSAs) may thrive as the ‘gold standard’ in securing the confidence of investors if the Philippines will ultimately decide on integrating nuclear power as a strategic component of its future energy mix, according to the Energy Regulatory Commission....
The pass-on tariff of power utility giant Manila Electric Company (Meralco) will climb by a marginal P0.0229 per kWh in the March billing cycle, and that has been precipitated mainly by the ancillary services (AS) charges of the power system operator. The slight hike in charges will drive up...