The P68.2-billion Metro Rail Transit Line 7 (MRT-7) is 62.1 percent complete and will partially operate this year, two decades after the project's unsolicited proposal was submitted, according to a statement from the Department of Transportation (DOTR). media The unsolicited proposal for the MRT-7...
The Quezon City local government on Friday, Dec. 10, opened a zipper lane on Commonwealth Avenue due to the construction of the Metro Rail Transit-7 (MRT-7) Manggahan Station on the major thoroughfare. The construction activities (establishment of columns and relocation of utility lanes and...
media San Miguel Corporation (SMC) recently mounted two more brand new Hyundai Rotem train sets on its 22-kilometer, P68.2 Billion Metro Rail Transit Line 7 (MRT 7) and is on track to start operating next year. This was the second batch of train sets, after the first arrived from Korea last month....
The eastbound portion of North Avenue in Quezon City will be closed to traffic starting next week until June 2022 for the construction of the Metro Rail Transit Line 7 (MRT-7). MMDA/MANILA BULLETIN In an advisory, the Metropolitan Manila Development Authority (MMDA) said that the closure of the...
San Miguel Corporation (SMC) unloaded and installed the first trainset for its P68.2 Billion Metro Rail Transit Line (MRT-7) in Quezon City this weekend, with the second arriving at the project site Monday, Sept. 12. smc mrt delivery2 The trainsets consisting of three cars each, were ordered from...
San Miguel Corporation (SMC) today ( (Sept. 1) announced that the first batch of trains for its MRT-7 project will arrive from South Korea next week, with the entire railway slated to be finished in 2022. SMC-MRT2 The trains, which consist of six cars or two trainsets procured from Hyundai ROTEM,...
The P68.2-billion Metro Rail Transit Line 7 (MRT-7) is 60.93 percent complete and will partially operate in April 2022, over two decades after the project's unsolicited proposal was submitted. The 22-kilometer railway running from North Avenue in Quezon City to San Jose Del Monte in Bulacan will be...
The P63 billion MRT-7 is halfway complete, with civil works now 51.73 percent finished and electrical/mechanical (E&M) works 55.31 percent done. At last, almost two decades after the project's unsolicited proposal was submitted, the MRT-7 is opening next year. SMC president and COO Ramon...