DAVAO CITY – Apo Agua Infrastructure Inc. is set to complete the Davao City Bulk Water Supply Project this year.
Apo Agua is currently leading the construction of the Davao City Water District's (DCWD) Bulk Water Supply Project which will provide 300 million liters of safe water daily to over one million people here.
Apo Agua said that the company made the decision in response to delays in the project's construction timeline caused by complications brought about by the pandemic and other internal factors.
The project’s engineering, procurement, and construction contractor, J.V. Angeles Construction Corp. (JVACC), earlier had full responsibility for the construction works.
With Apo Agua in the lead, it would aggressively pursue as many construction work streams as possible, in parallel with each other, as the main catch-up strategy.
Despite a very tight timetable, the company targets project completion by the end of 2022, considering a swift and seamless transition.